View Details of Code :: 121.5

121.5: Revised Estimates permissible excess & change of scope

Code No.

Particulars

Date

Circular/

Guideline No.

121.5.30

Change in scope, specifications and design of sanctioned Project on National Highways – prior approval of Ministry

9.9.2002

RW/NH-33044/10/2002/S&R (R)

121.5.29

Regularisation of cases wherein expenditure has exceeded sanctioned cost but is within 15% of the sanctioned cost or Rs.1 crore whichever is less - regarding

30.10.2001

PAO/NH/DPP/2001-02/1677-83

 

121.5.28

Permissible excess of expenditure over estimates sanctioned (Original works) after 13th January, 2000

29.10.2001

RW/NH-11026/2/99-U.S(D.I.)

 

121.5.27A

Permissible excess of expenditure over estimates sanctioned (Original works) after 13th January, 2000

13.1.2000

RW/NH-11026/2/99-U.S(D.I.)

 

121.5.27

Submission of revised estimates for National Highway Works

9.11.1999

RW/NH-11026/1/99- US(D.I.)

 

121.5.26

Sanction of revised estimates for National Highway Works

7.9.1999

RW/NH-31019/4/94- DO II

 

121.5.25

Revised Estimates

7.9.1999

RW/NH-31019/4/94- (DO II)

 

121.5.24

Revised cost estimates in respect of National Highway (Original) works upto Rs.50 lakhs-sanction reg.

27.8.1997

RW/NH-11026/2/97- DO I

 

121.5.23

 

 

 

121.5.22

 

 

 

121.5.21

Procedure for submission of revised estimates requiring approval of Expenditure Finance Committee

27.1.1994

RW/NH-11026/1/94- DO I

121.5.20

Expeditious acceptance of tenders for works on National Highways.

26.9.1990

RW/NH-11026/1/89 DO I (Pt)

 

121.5.19

Processing of revised estimates for works on NHs or under other centrally financed schemes.

1.12.1989

RW/NH-11026/1/89 DO I

 

121.5.18

Submission of RE for Works of NHs Periodical review of expenditure/coDstruction period arid physical progress on works-avoidance of incurring expenditure beyond permissible limits without prior approval.

13.3.1987

NH III/P/25/78

 

121.5.17

Submission of Revised Cost estimates

 26-12-1985

NH III/P/25/78

 

121.5.16

Submission of Revised Cost estimates for various projects

26-12-1985

NH III/P/25/78

 

121.5.15

Submission of Revised Estimates

5.7.1985

NHIII/P/25/78

121.5.14/121.6

Recommendations of Vohra Committee-Prior Approval for Changing Scope of Sanctioned Estimates

19.5.1984

RW/NHIII/Coord/32/84

121.5.13

Recommendations of Vohra Committee-Revised Estimate Submission

5.4.1984

RW/NHIII/Coord/38/84

121.5.12/121.6

Prior Approval of Excesses Revised Estimate

14.7.1981

D.O. No. B-30 (41)/81

121.5.11

Preparation of Detailed Project Estimates for NH (R&B) Works-Avoidance Revision

30.12.1980

NHIII/P/10/80

121.5.10/(130)

Submission of Revised Estimates for NHs etc.

19.1.1980

PL-30 (6)/80

121.5.9

Submission of Revised Estimates for Works on NHs-Periodical Review of Expenditure/Construction Period & Physical Progress of Works

12.11.1979

NHIII/P/25/78

121.5.8/(121.4)

Submission of Cases to Expenditure Finance Committee Inspections Regarding-Procedure for Processing of Revised Estimates Costing Rs 1 crore and above

8.9.1978

NHIII/P/16/76

121.5.7

Submission of Revised Estimates for Works on NHs

24.5.1978

NHIII/P/25/78

121.5.6/(121.2)

Avoidance of Revision

28.10.1977

NHIII/P/31/77

121.5.5/(130)

Clauses in Revised Estimates Sanction on Cancellation of Contract

6.7.1977

NHIII/P/14/77

121.5.4A

Permissible excess of expenditure sanction

18.10.1976

PL-30 (193)/71

121.5.4

Revised Estimates of NH (R&B) Works : Check-Lists

1.7.1976

NHIII/P/50/76

121.5.3

Permissible Limit in Respect of NHs

2.2.1976

PL-30 (110)/74

121.5.2

Adjustment of Expenditure on NHs

25.9.1974

PL-30 (110)/74

 

121.5.1

Submission of Revised Estimates in Respect of NH Works-Procedure for

28.7.1972

NHIII-33(20)/72